Not a Partner?    Register here.

Why Fly YXC?

One stop service to most major cities in the United States

Facility

Map

 

AIRPORT LOCATION:

Canadian Rockies International Airport is located on Airport Access Road, a short distance off Highway 95A, approximately 15 km from Cranbrook and 20 km from Kimberley.

 

  • From Creston and Cranbrook, take Highway 95A as you exit Cranbrook to the North.
  • From Invermere and Fernie, take the Highway 95A exit prior to entering the city.
  • From Kimberley, exit left onto Airport Access Road from Highway 95A.

 

 

AIRPORT EXPANSION TIMELINE

 

April 28, 2008

International Departures area opens.

 

April 2, 2008

Delta Airlines deal announced! An agreement has been reached with Delta Airlines to provide non-stop international service between Canadian Rockies International Airport and Salt Lake City, Utah. The two hour trip between Cranbrook and Salt Lake City will enable East Kootenay residents to connect seamlessly to Delta flights anywhere in the world while at the same time, open massive new markets for regional tourism products. Flights will commence December 17, 2008.

 

January 14, 2008

Canada Border Services Agency (CBSA) takes possession of their new Customs and Immigrations facility at the airport. The new permanent location will staff full time Customs agents as part of the overall airport expansion strategy. 

 

October 16, 2007
International Arrivals area opens.

 

May 31, 2007
Work on the Air Terminal Building continues to progress. International arrivals area scheduled to open mid October.

 

October 23, 2006
Runway project completed with ZERO delays or cancellations to scheduled air traffic as a result of the expansion program. Instrument Landing System commissioning completed by NavCanada and now fully operational.

 

October 12, 2006
8,000 foot runway opens
and operating at full length.

 

July 17, 2006
Earthworks move to the south end of the runway as the north footprint is complete. Paving of the north runway expected to commence August 1.

 

June 5, 2006
Construction commences on the new Air Terminal Building international arrivals area including Canada Border Services Agencies new Customs facility.

 

May 1, 2006
Construction on the north end of the runway project commences with earth works and drainage/electrical works.

 

April 24, 2006
Cranbrook City Council awards the Air Terminal Building contract to Tri City Contracting of Kamloops, British Columbia.

 

April 24, 2006
Cranbrook City Council awards Phase 2 Runway Paving and Electrical to Interoute Construction of Crescent Valley, British Columbia.

 

April 14, 2006
Federal funding in the amount of $4.5M is announced during a special ceremony at the airport by Jim Abbott, Member of Parliament for the Kootenay/Columbia Region.

 

March 13, 2006
Cranbrook City Council awards Phase I Earth Works and Utilities contract to Mackay Contracting of Cranbrook, British Columbia.

 

February 24, 2006
Tender documents for the Air Terminal Building have been finalized and will be available to interested parties on Monday February 27th at YVR Airport Services offices in Vancouver and on Tuesday February 28th at the Airport Manager’s office in Cranbrook.

A plan room will be set up at the Airport Management’s Office (9:30 am to 4 pm Monday to Friday) and all information will also be posted in the BC Construction Association’s electronic plan room.

The tender closing date and time is: Tuesday, April 4th, 2006 at 2:00:00 pm, Vancouver time.

 

February 12, 2006
Tender documents for Phase 2 - Runway Paving and Electrical have been finalized and issued. Click HERE for more information and tender documents download page.

The tender closing date and time is: Tuesday, March 7th, 2006 at 2:00:00 pm, Vancouver time.

 

February 10, 2006
Tender documents for Earthworks and Utilities have been finalized and issued. Click HERE for more information and tender documents download page.

The tender closing date and time is: Tuesday, February 28, 2006 at 2:00:00 pm, Vancouver time.

 

January 9, 2006
McFarlane Green presented 50% terminal building design to Cranbrook City Council including artist renditions of the terminal building layout. YVRAS Project Manager Kevin Johnston delivered a positive budget update and status report on the runway project.

 

December 15, 2005
Both Terminal Building and Airside design continue to progress with 50% design of Air Terminal Building complete and 25% of Runway design complete.

 

November 24, 2005
Western Economic Diversification agrees to fund 95% of a $130,000 International Strategic Marketing initiative to promote the airport in advance of the scheduled Spring 2007 completion date. Area resorts have agreed to fund the remaining 5%.

 

October 16, 2005
McFarlane Green Architects complete the value engineering study on the Air Terminal Building options resulting in Cranbrook City Council's decision to pursue the recommended option to renovate and expand the existing facility.

 

September 19, 2005
Cranbrook City Council hires Associated Engineering as successful proponents for runway extension design and construction services.

 

August 25, 2005
The City of Cranbrook hosts a "Sense of Place" seminar with community leaders and stakeholders to explore regional options for terminal building design themes.

 

August 15, 2005
Cranbrook City Council approves the new 8000-foot runway configuration by adding 1500 feet to the north end and 500 feet to the south end to facilitate direct flight from North America and limited European operations.

 

July 18, 2005
City of Cranbrook hires McFarlane Green Architects as successful proponents to design an expanded air terminal building.

 

April 17, 2005
Provincial funding in the amount of $4.5M is announced during a special ceremony at the airport by Bill Bennett, MLA for the East Kootenay Region.